Onsite visit to the TPP-2 of JSC Astana-Energiya

*The number of seats is strictly limited. The terms of participation can be found by contacting the Organising Committee.

On 29 June 1971, a special decision was made by the USSR Ministry of Energy to develop the technical design of the Tselinograd TPP-2. Construction of the 1st stage of the TPP-2 began in 1972 and was completed in 1985. On 29 August 1979, the documents on the commissioning of the 1st unit of the 1st stage of the Tselinograd TPP–2 were signed. To date, the plant has 8 steam, 6 hot water boilers and 6 turbine units with an installed electric capacity of 600 MW. Since the commissioning of the TPP-1 and TPP-2 stations, more than 72 mil kilowatt/ hour of electric energy have been generated as of 31.12.2020. The TPP-2 is the largest thermal power plant in Astana.

The installed capacity is:

  • Electric - 600 MW
  • Thermal - 2,106 Gcal/hour

The main equipment includes:

  • Power boiler BKZ-420-140-5
  • Power boiler E-550-13,8- 560KT
  • Hot water boiler KV-T-139,6-150
  • Turbine unit PT-80/100-130/13
  • Turbine unit T-120/130-130-8

The tour will be conducted by Ualikhan Askarbekov, Head of TPP-2.

Registration request for the onsite visit

    Please note that due to our internal policy we are not entitled to send any materials to personal emails (Yahoo, Yandex, Google, etc.)

    If you have any questions, please contact us:

    +44 207 394 3090 (London)

    Where did you hear about this event?